COMPLETION!!
The remodelled chancel from the front The remodelled chancel from the rear
The new site for the organ console The easy access ramp
The revised layout of the Lord’s Table The south aisle and repositioned font
The new vestibule kitchen area The new boiler and sink arrangement
Jonathan and Ros operating the PA and AVA equipment in their new position
WORK IN PROGRESS!!
Week 5 – Replastering of the walls is complete, and the font is installed in its new position
Week 5 – A view of the old font in its new position together with the new access ramp
Week 5 – The chancel extension is now well under way.
Week 5 – The new sub-floor is complete awaiting laying of the new oak flooring
Week 5 – The last of the master cable runs and access points being installed
Week 5 – The disabled access ramp steels are installed, as is the base for the old font.
Week 4 – A panorama view of recent work to the nave and upper chancel showing initial work to the sub-floors, the base of the chancel extension and the main cable ducts.
Week 4 – The initial sub-floors to the North and West aisles are almost complete.
Week 4 – Remedial work to resolve damp penetration to the South aisle is well underway.
Week 4 – Cable ducting being laid for the PA/AVA equipment and new power circuits.
Week 4 – The scope of damp penetration prior to its repair.
Week 4 – The main worship and bell tower areas being readied for new flooring.
Week 3 – Clearance of the old church flooring and joists is now complete.
Week 3 – The existing heating pipes are being relocated in readiness for extra radiators.
Week 3 – The poor condition of the under floor voids can be seen quite clearly.
Week 3 – The view from the South aisle.
Week 2 – Clearance of the church is almost complete with pews, PA and AVA equipment now removed ready for the builders arrival on Monday
Week 2 – Worship taking place in the Church Centre (6:30pm Holy Communion)
Week 1 – The pews in the process of being removed.
Week 1 – The chancel in the process of being stripped of furniture and fittings.
Week 1 – The organ is removed for cleaning, restoration and safekeeping.
Saint Michael’s prior to the development phase commencing